The power plant provides more than 10% of the country’s electricity and meets the EU’s strictest environmental and safety standards
ContourGlobal Maritsa East 3 TPP is ready to operate at full capacity in the coming winter months after the completion of the annual maintenance of its four power units. The power plant provides on average more than 10% of the country’s electricity, meeting the strictest European standards for environmental protection and safety. In the first six months of 2022, it reached 12.3% – this is the average consumption of more than half of Bulgarian households.
ContourGlobal Maritsa East 3 TPP fully meets the requirements of European legislation for environmental protection and safety. After the last modernization, completed in August 2021, the specialized desulphurization installations provide an even higher level of flue gas purification. To date, BGN 1.4 billion has been invested in the power plant for environmental improvements, modernization, requirements for safety and health.
Thanks to large-scale rehabilitation and modernization, ContourGlobal Maritsa East 3 TPP is the first power plant in the South-Eastern Europe region that meets the strictest European standards for environmental protection and safety. For 12 years, it has also successfully defended its certifications according to the international standards for environmental management and health and safety at work, ISO 14000:2015 and ISO 45001:2018 (previously – OHSAS 18001:2007).
“As one of the largest production facilities in Bulgaria, which operates entirely with local resources, our power plant is a key element of the country’s electricity system. We also fully comply with European safety and environmental regulations, which makes our role even more important. After the maintenance of the facilities, we are fully prepared to operate at full capacity to meet the electricity needs of Bulgarian consumers,” explained Alexander Zhelev, chief engineer at ContourGlobal Maritsa East 3 TPP.
The annual scheduled maintenance of the ContourGlobal Maritsa East 3 thermal power plant began in early June 2022. The preventive maintenance of the facilities ensures the efficient and safe operation of the power plant during the autumn and winter seasons, when loads are traditionally greater due to low temperatures and high electricity consumption.
The repair activities, for which external contractors were additionally engaged, were carried out under the strictest measures for the safety of facilities, processes and people. In the course of the repair campaign, on the territory of the power plant dozens of external subcontractors and over 1,000 of their staff took part, as well as engineers and specialists of ContourGlobal, the management of the thermal power plant announced.
With an installed capacity of 908 megawatts (MW), the ContourGlobal Maritsa East 3 TPP is the second largest thermal power plant in Bulgaria. It works entirely with local raw materials, using 25% of the lignite coal mined by Maritsa East Mines and thus contributes to guaranteeing the energy security of the country, which is of particular significance at the present moment.